Description
The centrepiece of the B&P Tunnel Replacement Program is the Frederick Douglass Tunnel (FDT), which will improve Amtrak’s North-East corridor by establishing a new, additional route through Baltimore, Maryland connecting the existing Baltimore Penn Station with points south and the port of Baltimore. As part of Design Package F2 – South Approach Utility and Roadway Relocations, South of Lafayette Avenue, the relocated storm drain, sanitary drain and water main will need to cross underneath the existing Amtrak NEC tracks. The contractor proposed an Alternate Technical Concept (ATC) to install and house all three main utility lines in one single tunnel. The Siphon tunnel excavation was performed by using the traditional drill & blast method, with subsequential installation of steel support sets, timber lagging, and rock bolts, as required.
Geology
Rock mass is composed of fresh, very hard, foliated, fractured rock with cubic jointing pattern, characterized as a dark quartz-rich gneiss with millimetric grain size, homogenous.